Cost of changes at high school 'concerning'

METHUEN — City and school officials generally are pleased with progress on the roughly $100 million high school renovation project, but some say change orders on the project need to be watched.

Earlier this month, local officials monitoring the project questioned contractor Consigli Construction and project management company Trident Group when the officials were presented with several change requests, some for work completed last fall. City Councilor Ron Marsan, a member of the committee overseeing the renovation, told his fellow councilors the costs of changes were concerning.

“In the scope of the project it’s not alarming, but it’s becoming concerning,” he said at the last City Council meeting.

So far, the renovation and expansion project, which started in earnest last summer, has spent about $28 million, according to City Auditor Thomas Kelly. To date, requests for changes to the plans total about $1.29 million, or about 4.6 percent of the total amount spent so far and about 1.4 percent of the total project.

“The big picture is you have this major project, and 1.4 percent total for change orders is pretty good,” Kelly said.

The project’s budget included about $8 million, or 8 percent of the total, for unforeseen changes, which Marsan, a local contractor, and Gino Baroni, owner of Trident, said is a typical-sized contingency fund.

On Wednesday, Baroni told the Building Committee that especially given the turbulence of the project a year ago, when the city fired contractor Dimeo Construction because of escalating costs, the budget and schedule is “by and large in good shape.”

Baroni and representatives from Consigli presented committee members with a detailed breakdown of the changes and the reasons behind them on Wednesday, a move that addressed members’ concerns. They promised to continue presenting similar breakdowns.

Kelly told the City Council he is watching the changes closely to keep an account of which changes qualify for a 68-percent reimbursement from the state and which must be wholly paid for by the city. City and project officials plan to meet on March 20 with the Massachusetts School Building Authority to review the changes and get more solid answers on which changes can be reimbursed.

Text Only | Photo Reprints
Latest News

AP Video
Johnson: Six Arrests, No Tear Gas in Ferguson Raw: Rescue, Relief Efforts at Japan Landslide Cadavers, a Teen, and a Medical School Dream Raw: Woman Escorted From Ferguson Protests California Drought Stings Honeybees, Beekeepers Officer Who Pointed Gun at Protesters Suspended Holder Hopes to Bring Calm to Ferguson Today in History August 21 Holder Pledges Top Investigators for Ferguson US Mission to Rescue Hostages in Syria Failed Manfred, Torre and MLB Take Ice Bucket Challenge Bank of America Reaches Record $17B Settlement Holder Reassures Ferguson Community With Visit GlobalPost CEO Remembers Foley As a Brave Man Seth Meyers Rolls Out Emmy Red Carpet Obama: World Is Appalled by Murder of Journalist Israel, Militants Trade Fire After Talks Fail Pres. George W. Bush Takes Ice Bucket Challenge Pierce Brosnan's Call to Join the Expendables Changes Coming to No-Fly List